EAZET is an environmentally friendly pile method with low noise, low vibration, and no waste soil. The installation process is extremely simple. Works by a compact machines less than 10m height are safe and executing speedy pile installation.
EAZET pile Standard installation Process

- 1.?Attach a pile to torque motor
- 2. Set the pile to the planned location.
- 3. Begin rotation while applying downward crowd
- 4. Add extension sections if necessary
- 5. Completion of the pile installation
EAZET work on site
Standard EAZET installation
-
1. Delivering the pile machine.
-
2. Enter the construction site.
-
3. Deliver EAZET piles.
-
4. Setting the EAZET pile.
-
5. Centering of pile.
-
6. EAZET pile installation without waste soil.
-
7. Connect the piles.
-
8. Continue or finish the installation.